Another development with Edgar Taylor who we have worked with closely for years.

This first phase of this works was to form a tarmac access road to the site to give access to the site compound. The compounds was formed on the grass with a georgic and sacrificial stone layer.

Works then proceeded to the inside where we are reduce digging the floors to take a new insulated concrete slab with power float finish.

Internal drains now in and concrete ready to receive the power float floor.

Concrete floors prepped and concrete being pumped into our new slabs ready for power floating.

External works complete along with the sand stone steps to the main entrance.




 
 
 
  • Facebook Social Icon
  • googlePlaces
  • twitter

27 Bankside, Kidlington OX5 1JE, UK

Tel -01865 377333

©2025 by Keith Cook Construction Ltd.

Proud Sponsors Of Oxford Speedway

Screenshot 2025-03-21 at 09.29.29.png
bottom of page