Quad 1 Foundations

  • Writer: John Cook
    John Cook
  • Apr 5, 2017
  • 1 min read

Foundations and the external ring beam are progressing well and should be complete in the next week. This will allow preparation to begin to the concrete floor. Providing there are no changes the ground floor should be in by the end of the month.

Next phase is the Pavilion foundations which start this week and completed by end of next.

 
 
 